A hotel operating statement steps down from total revenue through five profit lines. The line your incentive management fee is calculated from will cost you, or save you, far more than the fee percentage most owners spend their time negotiating.

I have watched owners negotiate an operator down from 10 percent to 8 percent, shake hands feeling good about it, and then agree to calculate that 8 percent off the wrong line- giving back everything they won, and more.

I founded HVS and have spent more than 40 years valuing hotels and negotiating management contracts. In this issue, I’ll walk through how to structure the incentive fee, including the one provision that protects you when the hotel underperforms, using real numbers from a real operating statement.

The incentive fee is the operator’s profit

Start with a point most owners never stop to consider. An operator can typically cover its entire cost of managing your hotel: corporate overhead, support staff, reservation systems, plus a modest profit, from the base management fee alone. The base fee is a percentage of gross revenue and is paid whether the hotel makes money or not.

That means the incentive fee is not compensation. It is the operator’s profit.

Seen that way, the owner’s position is straightforward: the operator should not earn its profit until the owner has earned a return.

Five profit lines, two opposing interests

The industry reports under the Uniform System of Accounts for the Lodging Industry (USALI), so every operating statement is built the same way. In a negotiation, that is an advantage — both sides are reading the same map.

Figure 1 — The USALI profit lines, and where each side wants the incentive fee calculated

  • Departmental Profit — total revenue less the direct cost of each revenue department. Rarely used in management contracts.

  • Gross Operating Profit (GOP) — after undistributed expenses: administrative and general, sales and marketing, property operations and maintenance, utilities, and IT. This is where operators want the fee calculated.

  • Income Before Non-Operating Income and Expenses — after the base management fee.

  • EBITDA — after property taxes and insurance, and including non-operating income such as rent from antennas, billboards, or leased retail space.

  • EBITDA Less Replacement Reserve — after the FF&E reserve. The bottom of the statement, and where owners want the fee calculated.

The owner wants the fee calculated from the lowest line; the operator wants the highest. That tension is the entire negotiation.

The operator’s case for GOP

Operators push hard for Gross Operating Profit, and their argument deserves respect. Everything above the GOP line is genuinely under their control: they generate the revenue and manage the expenses. Below it, they are not. Property taxes are reassessed, insurance premiums move, and an owner’s decision to renovate or add leverage can reduce net income through no fault of the operator.

“Don’t pay me on something I can’t control” is a sound position. Dismiss it, and you lose credibility at the table; credibility you will need later.

The owner’s case: the costs the statement never shows

The operating statement stops at EBITDA less replacement reserve. It says nothing about the two highest costs of owning a hotel: mortgage debt service and the return on the capital invested.

For a new hotel, that return is typically measured against total project cost, including land. For an existing hotel, it is measured against property value. Note that a return on invested capital already contains both a mortgage and an equity component, so debt service should not be added on top of it.

Covering those costs before the operator earns a profit isn't aggressive. It is the order in which the money has to work.

Putting numbers on it

Consider a hotel producing EBITDA less replacement reserve of $9,254,000. To value it, we capitalize that income at the weighted average cost of capital: a 65 percent mortgage at 7 percent interest over 25 years (an 8.5 percent mortgage constant), and a 35 percent equity position seeking a 12 percent cash-on-cash return.

Figure 2 — A 9.7% capitalization rate produces a property value of $95.4 million

There are three ways to express what the owner needs to receive first:

Figure 3 — Debt service, return on cost, and return on value compared

  • Debt service: 65% of $95.4 million is a $62.0 million mortgage. At an 8.5% constant, annual debt service is $5,271,000.

  • Return on cost: a total project cost of $85.5 million (roughly $350,000 per key) at a 7% return is about $6.0 million.

  • Return on value: $95.4 million at a 7% return is $6,678,000.

The return on value is the largest of the three, making it most advantageous to the owner. In an ideal world, the incentive fee would be a percentage of EBITDA less replacement reserve, less a $6,678,000 return on value.

Breaking the standoff: the owner’s priority

So the parties are at a standoff. The owner wants the fee calculated at the bottom of the statement; the operator will not go below GOP, for defensible reasons. Most owners either concede here or spend their leverage on an argument they cannot win.

The provision that resolves it is the owner’s priority.

The operator calculates the incentive fee from GOP, exactly as it prefers. But the fee is not paid until the owner has first received a threshold amount of cash flow. In contract terms, payment of the incentive management fee is subordinated to an owner’s priority. The operator keeps the clean, controllable calculation; the owner keeps its return. Neither side abandons its principle—which is precisely why this provision is agreed to.

  • Form: a fixed dollar amount (say, $6 million a year) or a percentage of the owner’s investment (such as 7% of value). I prefer the percentage.

  • Position in the waterfall: paid from cash flow after operating expenses, the replacement reserve, and the base fee, but before any incentive fee.

  • Adjustments: build in periodic resets for inflation, significant capital upgrades, market conditions, or changes in performance. Over a 20-year contract, a number that was fair in year one can be meaningless by year fifteen.

How it works in practice

Back to our hotel. The incentive fee is 8 percent of GOP, or $978,000. The owner’s priority is the return on value, $6,678,000.

Figure 4 — The owner’s priority in a strong, soft, and weak year

  • In a strong year, $9,254,000 minus the $6,678,000 priority leaves $2,576,000 available—more than enough. The operator receives its full $978,000, and the owner keeps $1,598,000 above the priority, for a total of $8,276,000. On a $95.4 million asset, that is an 8.7 percent return. Everyone does well.

  • In a soft year, with cash flow of $7,000,000, only $322,000 is available to pay an incentive fee that would otherwise have been $978,000.

  • In a weak year, at $6,300,000, nothing is available. The operator earns no incentive fee.

That is the provision working exactly as designed. In a bad year, the operator’s profit disappears before the owner’s return does. Without it, the owner would be writing a $978,000 check out of a $6.3 million result — in the year it could least afford to.

Three terms to settle before you sign

Figure 5 — Contract choices and how each affects the owner

What happens to an unpaid incentive fee? It can be forfeited, deferred to a future year with sufficient cash flow, or deferred with interest. Negotiate for forfeiture and accept deferral if you must. Be very careful with accrual; it builds a liability that tends to surface at the worst possible moment, which in my experience is usually the day you decide to sell.

Is the owner’s priority cumulative? A cumulative priority carries any shortfall forward, so the operator earns no incentive fee until the owner has been made whole for prior years. A non-cumulative priority resets annually, and the shortfall is lost. Cumulative is meaningfully better for the owner, and it is negotiable far more often than owners assume.

Priority or debt service? Lenders sometimes ask for the incentive fee to be subordinated to debt service instead. It sounds like the same protection, but it is not. Debt service changes when you refinance, when rates move, and as principal is paid down, and your protection moves with it, sometimes downward. A priority based on the value or cost of the hotel can remain stable for the life of the contract.

Four points to take into the negotiation

Figure 6 — Converting the incentive fee from a share of revenue to a share of GOP

  1. Negotiate the base and incentive fees as a single package. Settle the base fee first, and you've used up your leverage. Decide the total fee you are willing to pay, then divide it, pushing as much as possible into the incentive portion, which is only paid when the hotel performs.

  2. Do the arithmetic before the meeting. If 6 percent of total revenue is a market-level total fee, a 3 percent base and 3 percent incentive equates to an 8 percent incentive fee on GOP (at a 37.5 percent GOP margin). Lower the base to 2 percent, and the incentive rises to roughly 10.7 percent of GOP — the same total cost, with substantially better alignment. Rebuild the table as the GOP assumption changes.

  3. Ramp the base fee over the opening years. Roughly 1 percent in year one, 2 percent in year two, and 3 percent by year three. It is one of the easiest provisions to win, and most operators expect to concede it. Ask for five years.

  4. Read the definition of Gross Revenues word by word. Every dollar struck from that definition puts two to four cents back in your pocket. Operators should not earn a fee on revenue they do not manage, and this definition is where a great deal is quietly decided.

The broader lesson

A typical management contract contains roughly 40 more provisions built just like this one, in my course on selecting a hotel operator and negotiating the management contract— where the standard draft looks perfectly reasonable, and a single defined term or cross-reference quietly decides who gets the money: termination rights and the true cost of a buyout, radius restrictions, ownership of guest data, fees when the hotel is damaged or condemned, and the performance test that determines whether you can actually remove an underperforming operator.

View story source
Finance Development Operations & Strategy Owner Partnerships Owner's Priority GOP Revenue Management Incentive Management Fee

As a leading authority and prolific author on the topic of hotel valuations and feasibility studies, and the Founder of HVS, Steve Rushmore has written all six textbooks and two seminars for the Appraisal Institute covering this subject and is known as the “Creator of the Hotel Valuation Methodology.” He has also authored three reference books on hotel investing and has published more than 300 articles.

Hotel Market Analysis and Valuation Software was developed by Steve Rushmore for his firm- HVS. It has been enhanced by Professor Jan deRoos of the Cornell Hotel School. This software has been the most downloaded product on the Cornell website and is used by thousands of hotel professionals around the world. The software is designed specifically to assist in the preparation of hotel market studies, forecasts of income and expense, and hotel...

Comments

Comments for this content

0 comments available
Loading comments...